Question 726 - PMP discussion
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
A.
Product backlog, budget, resource management plan
B.
Budget, minimum viable product (MVP), retrospective notes
C.
Resource management plan, retrospective notes, backlog grooming
D.
Backlog grooming, product backlog, minimum viable product (MVP)
Your answer:
0 comments
Sorted by
Leave a comment first