Question 739 - PMP discussion
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
A.
Request the scrum team to prioritize the product backlog
B.
Ask the product owner to prioritize the backlog with the project team
C.
Call for an internal meeting to discuss the changes and their value
D.
Incorporate the changes in the last sprint before the first release
Your answer: