A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.

What should the project manager do?

A.
Review and reassign team assignments
Answers
A.
Review and reassign team assignments
B.
Facilitate communication and team building
Answers
B.
Facilitate communication and team building
C.
Negotiate for new team members
Answers
C.
Negotiate for new team members
D.
Review and update the communications management plan
Answers
D.
Review and update the communications management plan
Suggested answer: B