A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

A.
Implement new options
Answers
A.
Implement new options
B.
Examine the team's virtual needs
Answers
B.
Examine the team's virtual needs
C.
Rectify ground rule violations
Answers
C.
Rectify ground rule violations
D.
Review performance formally
Answers
D.
Review performance formally
Suggested answer: B