Question 736 - PMP discussion
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible.
The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
A.
A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
B.
A hybrid approach will allow the project manager to revise the product specifications
C.
A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
D.
A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
Your answer:
0 comments
Sorted by
Leave a comment first