A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible.

The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

A.
A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
Answers
A.
A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
B.
A hybrid approach will allow the project manager to revise the product specifications
Answers
B.
A hybrid approach will allow the project manager to revise the product specifications
C.
A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
Answers
C.
A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
D.
A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
Answers
D.
A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
Suggested answer: C

Explanation:

Without knowing what is the requirement, as a project manager you cannot plan or schedule.

Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.