Question 735 - PMP discussion
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
A.
Meet with the design team manager to inform them of the current status and request an additional designer
B.
Ask the software engineer to move forward without completing the important feature
C.
Contact the design team manager and ask to reconsider the priority list based on the latest situation
D.
Meet with the designer to share the current status and develop a solution to complete the task