Question 734 - PMP discussion
A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.
What should the project manager do?
A.
Include the customer in daily project activities to gain the required guidance
B.
Plan ahead and define the best way to review the deliverables with the customer
C.
Request the customer to clarify all requirements at the start of each iteration
D.
Ask the customer to review the deliverables in each iteration based on their availability
Your answer: