A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

A.
Include the customer in daily project activities to gain the required guidance
Answers
A.
Include the customer in daily project activities to gain the required guidance
B.
Plan ahead and define the best way to review the deliverables with the customer
Answers
B.
Plan ahead and define the best way to review the deliverables with the customer
C.
Request the customer to clarify all requirements at the start of each iteration
Answers
C.
Request the customer to clarify all requirements at the start of each iteration
D.
Ask the customer to review the deliverables in each iteration based on their availability
Answers
D.
Ask the customer to review the deliverables in each iteration based on their availability
Suggested answer: B

Explanation:

Customers are often absent and reviews are often delayed resulting in increased rework, find the best way to review deliverables, involve customers, provide early feedback and make adjustments