Question 731

Report
Export
Collapse

A project manager works at an organization that is transitioning to agile. The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

Advise the project management office (PMO) to use the burndown chart as the single communication channel.
Advise the project management office (PMO) to use the burndown chart as the single communication channel.
Develop a communications management plan for each category in the stakeholder register.
Develop a communications management plan for each category in the stakeholder register.
Include the burndown chart in a monthly report that is distributed to all stakeholders.
Include the burndown chart in a monthly report that is distributed to all stakeholders.
Postpone the recommendation since the organization does not currently have a defined agile methodology.
Postpone the recommendation since the organization does not currently have a defined agile methodology.
Suggested answer: A
asked 23/09/2024
Andrea DG
35 questions

Question 732

Report
Export
Collapse

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Consult the risk register for an appropriate planned risk response and implement.
Consult the risk register for an appropriate planned risk response and implement.
Revise the project management plan and move the task to a time when the technical resource will be available.
Revise the project management plan and move the task to a time when the technical resource will be available.
Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
Update the lessons learned report and the risk log to reflect that this risk has materialized.
Update the lessons learned report and the risk log to reflect that this risk has materialized.
Suggested answer: A
asked 23/09/2024
Victor Cantu
36 questions

Question 733

Report
Export
Collapse

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer features or low quality.

What should the project leader have done to ensure success?

Asked the team to create an impediment log and keep it updated for use in the next sprint planning
Asked the team to create an impediment log and keep it updated for use in the next sprint planning
Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery
Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery
Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints
Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints
Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments
Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments
Suggested answer: D
asked 23/09/2024
John Kaye
29 questions

Question 734

Report
Export
Collapse

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

Include the customer in daily project activities to gain the required guidance
Include the customer in daily project activities to gain the required guidance
Plan ahead and define the best way to review the deliverables with the customer
Plan ahead and define the best way to review the deliverables with the customer
Request the customer to clarify all requirements at the start of each iteration
Request the customer to clarify all requirements at the start of each iteration
Ask the customer to review the deliverables in each iteration based on their availability
Ask the customer to review the deliverables in each iteration based on their availability
Suggested answer: B

Explanation:

Customers are often absent and reviews are often delayed resulting in increased rework, find the best way to review deliverables, involve customers, provide early feedback and make adjustments

Explanation:

asked 23/09/2024
Josiah Pardee
46 questions

Question 735

Report
Export
Collapse

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

Meet with the design team manager to inform them of the current status and request an additional designer
Meet with the design team manager to inform them of the current status and request an additional designer
Ask the software engineer to move forward without completing the important feature
Ask the software engineer to move forward without completing the important feature
Contact the design team manager and ask to reconsider the priority list based on the latest situation
Contact the design team manager and ask to reconsider the priority list based on the latest situation
Meet with the designer to share the current status and develop a solution to complete the task
Meet with the designer to share the current status and develop a solution to complete the task
Suggested answer: D
asked 23/09/2024
Tiffany Peterson
38 questions

Question 736

Report
Export
Collapse

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible.

The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
A hybrid approach will allow the project manager to revise the product specifications
A hybrid approach will allow the project manager to revise the product specifications
A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
Suggested answer: C

Explanation:

Without knowing what is the requirement, as a project manager you cannot plan or schedule.

Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.

Explanation:

asked 23/09/2024
yassine harbeg
34 questions

Question 737

Report
Export
Collapse

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

Implement new options
Implement new options
Examine the team's virtual needs
Examine the team's virtual needs
Rectify ground rule violations
Rectify ground rule violations
Review performance formally
Review performance formally
Suggested answer: B
asked 23/09/2024
Chun Yin Lau
44 questions

Question 738

Report
Export
Collapse

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.

What should the project manager do?

Review and reassign team assignments
Review and reassign team assignments
Facilitate communication and team building
Facilitate communication and team building
Negotiate for new team members
Negotiate for new team members
Review and update the communications management plan
Review and update the communications management plan
Suggested answer: B
asked 23/09/2024
fritz villanueva
48 questions

Question 739

Report
Export
Collapse

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

Request the scrum team to prioritize the product backlog
Request the scrum team to prioritize the product backlog
Ask the product owner to prioritize the backlog with the project team
Ask the product owner to prioritize the backlog with the project team
Call for an internal meeting to discuss the changes and their value
Call for an internal meeting to discuss the changes and their value
Incorporate the changes in the last sprint before the first release
Incorporate the changes in the last sprint before the first release
Suggested answer: B

Explanation:

While the Product owner is responsible for prioritizing the backlog, and in this case should collaborate with the team.

https://www.dumpsdiscuss.com/pmp-v1/what-should-the-project-manager-do-next-156/

Explanation:

asked 23/09/2024
Lin Joel
23 questions

Question 740

Report
Export
Collapse

Five agile teams working together on a product recently performed release planning. Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished.

What should the project manager have done differently?

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments
Performed a Scrum of Scrums on a regular basis to help the teams remove impediments
Formed a separate quality assurance team to test all items coming from each team at the end of each sprint
Formed a separate quality assurance team to test all items coming from each team at the end of each sprint
Arranged an online session on the integration concept and suggested tools to the teams
Arranged an online session on the integration concept and suggested tools to the teams
Ensured frequent and continuous integration of work to obtain early feedback and continuous learning
Ensured frequent and continuous integration of work to obtain early feedback and continuous learning
Suggested answer: D