PMI PMP Practice Test - Questions Answers, Page 72
List of questions
Question 711

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.
What should the project manager do to address this situation?
Question 712

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.
What should the project manager do?
Question 713

A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the organization and have varying levels of interest.
Which approach should the project manager use with the stakeholders?
Question 714

A project manager is working on an enterprise resource planning (ERP) implementation project that spans divisions within and outside the country. The project manager understands the importance of gate reviews and periodic checks.
Which of the following should the project manager leverage?
Question 715

A customer is concerned with the quality of the product delivery, as the production deployment is approaching.
What should the project manager do next to ensure acceptance of the deliverables?
Question 716

An agile team is brainstorming end prioritizing all of the risks according to severity.
What should the teem do about the identified risks?
Question 717

A project manager is working with the product owner and customer stakeholders on prioritizing the product backlog and planning the product delivery dates. The customer stakeholders are asking to include several deliverables as high priority. The product manager also has technical tasks that should be added as high priority.
What should the project manager do?
Question 718

A project has been successfully completed. The project was ahead of schedule, under budget, and delivered the expected benefits. The project sponsor was satisfied and distributed recognition certificates to key project team members.
However, the project sponsor accidentally forgot to issue a certificate to a key team member.
How should the project manager treat the missed key team member to avoid disappointment and demotivation?
Question 719

A customized module is being implemented into an off-the-shelf enterprise resource planning (ERP) solution. The project scope has been clearly defined by the sponsor, and the project manager is close to starting user acceptance testing.
However, the newly elected government introduced a significant package of taxation reforms.
What should the project manager do?
Question 720

A company operates on a 2-year budgeting cycle. The project manager has been assigned a high-visibility project to deliver a brand new, innovative capability. While the requirements for the new capability are defined, the solution design is only beginning. The project manager's boss is concerned that the final solution will exceed the budget for the project.
What should the project manager do next to anticipate the budget impacts of the solution?
Question