PMI PMP Practice Test - Questions Answers, Page 71
List of questions
Related questions
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.
What should the project manager do?
A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.
What should be used to prioritize the backlog items?
A project manager is leading a hybrid project that is building an app for a travel industry startup.
Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.
What should the project manager do first?
A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.
How should the project manager communicate with the local community?
During the execution of a project, a key stakeholder complains to the project manager about recent communications. The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.
What should the project manager do?
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months.
What should the project manager do first?
During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans.
What should the project manager do first?
A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.
What should the project manager do?
A project team is completing a design, while another team in a different country is performing implementation.
How should the project manager communicate the design to the implementation team?
Question