A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?
A.
Document the new stakeholders' concerns in the meeting minutes.
B.
Schedule an ad hoc meeting with the new stakeholders to discuss concerns.
C.
Use social media environments to share the project information
D.
Use the project management information system (PMIS) to share information.