Question 757 - PMP discussion

Report
Export

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved. Which distribution list should the project manager use when sending out invitations?

A.
Functional managers, team members, and external consultants with experience in the field
Answers
A.
Functional managers, team members, and external consultants with experience in the field
B.
Team members, engineers, and weather experts
Answers
B.
Team members, engineers, and weather experts
C.
Team members, consultants from outside the project with experience in the field, and the customer
Answers
C.
Team members, consultants from outside the project with experience in the field, and the customer
D.
Weather experts, functional managers, and team members
Answers
D.
Weather experts, functional managers, and team members
Suggested answer: B
asked 23/09/2024