Question 758 - PMP discussion
A junior project manager is excited to start working on their first project with a telecommunications company. A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.
Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)
A.
Organizational process assets (OPAs)
B.
Lesson learned registers from past projects
C.
Historical issue logs
D.
Project scope statement
E.
Project management plan
Your answer: