Question 760 - PMP discussion

Report
Export

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

A.
Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.
Answers
A.
Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.
B.
Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.
Answers
B.
Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.
C.
Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.
Answers
C.
Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.
D.
Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.
Answers
D.
Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.
Suggested answer: B