In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?
A.
Facilitate training on version control and project artifacts.
B.
Maintain separate document control via regions to avoid discrepancies.
C.
Maintain a central repository of artifacts with a version control system.
D.
Develop a document management software for version control.