Question 762 - PMP discussion
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
A.
Work with the project manager to develop a new approach that will bring benefits to the project
B.
Suggest using an agile approach since customer and team collaboration is critical for project success
C.
Establish a project management methodology that requires the customer to provide daily updates to the team
D.
Provide a project management template for the project manager to follow as a guide