Question 762 - PMP discussion

Report
Export

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

A.
Work with the project manager to develop a new approach that will bring benefits to the project
Answers
A.
Work with the project manager to develop a new approach that will bring benefits to the project
B.
Suggest using an agile approach since customer and team collaboration is critical for project success
Answers
B.
Suggest using an agile approach since customer and team collaboration is critical for project success
C.
Establish a project management methodology that requires the customer to provide daily updates to the team
Answers
C.
Establish a project management methodology that requires the customer to provide daily updates to the team
D.
Provide a project management template for the project manager to follow as a guide
Answers
D.
Provide a project management template for the project manager to follow as a guide
Suggested answer: B