A project manager is leading a large public project that will have a high impact on the town's citizens.

How should the project manager define the different requirements?

A.
Analyze the interests and influence of stakeholders and evaluate their requirements.
Answers
A.
Analyze the interests and influence of stakeholders and evaluate their requirements.
B.
Include only the key requirements and keep the stakeholders informed about scope decisions.
Answers
B.
Include only the key requirements and keep the stakeholders informed about scope decisions.
C.
Add only the opinions of the team, because they know the objectives of the project.
Answers
C.
Add only the opinions of the team, because they know the objectives of the project.
D.
Include only the common requirements of each stakeholder group in the project goals.
Answers
D.
Include only the common requirements of each stakeholder group in the project goals.
Suggested answer: A