Question 777 - PMP discussion

Report
Export

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

A.
Developed benchmarking
Answers
A.
Developed benchmarking
B.
Assessed feasibility and impacts
Answers
B.
Assessed feasibility and impacts
C.
Detailed the project charter
Answers
C.
Detailed the project charter
D.
Analyzed stakeholders
Answers
D.
Analyzed stakeholders
Suggested answer: D