A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

A.
Ensure the client representative is involved in the estimation.
Answers
A.
Ensure the client representative is involved in the estimation.
B.
Ensure that a 20% contingency is included in the estimation.
Answers
B.
Ensure that a 20% contingency is included in the estimation.
C.
Review the completion costs of similar projects.
Answers
C.
Review the completion costs of similar projects.
D.
Review the lessons learned from similar projects.
Answers
D.
Review the lessons learned from similar projects.
Suggested answer: C