Question 785 - PMP discussion
During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.
What should the project manager do?
A.
Cancel the current iteration and reschedule it with the dependent activity.
B.
Include the dependent activity in the current iteration for team B.
C.
Ensure team B prioritizes the dependent activity in iteration three.
D.
Assign the two critical activities to team B in iteration two.