A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes. The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

A.
Define and direct communication to influential stakeholders.
Answers
A.
Define and direct communication to influential stakeholders.
B.
Develop and define a communication strategy for stakeholders.
Answers
B.
Develop and define a communication strategy for stakeholders.
C.
Utilize a uniform communication structure across all groups.
Answers
C.
Utilize a uniform communication structure across all groups.
D.
Describe the four groups in the project stakeholder matrix.
Answers
D.
Describe the four groups in the project stakeholder matrix.
Suggested answer: B