List of questions
Related questions
Question 787 - PMP discussion
Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?
A.
Develop requirements and designs to support a faster product release.
B.
Emphasize the adoption of a predictive approach to minimize ambiguity.
C.
Recommend an agile approach so the project can be delivered iteratively.
D.
Outsource development of the product to a third party with more experience.
Your answer:
0 comments
Sorted by
Leave a comment first