Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

A.
Develop requirements and designs to support a faster product release.
Answers
A.
Develop requirements and designs to support a faster product release.
B.
Emphasize the adoption of a predictive approach to minimize ambiguity.
Answers
B.
Emphasize the adoption of a predictive approach to minimize ambiguity.
C.
Recommend an agile approach so the project can be delivered iteratively.
Answers
C.
Recommend an agile approach so the project can be delivered iteratively.
D.
Outsource development of the product to a third party with more experience.
Answers
D.
Outsource development of the product to a third party with more experience.
Suggested answer: C