List of questions
Related questions
Question 788 - PMP discussion
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?
A.
Report the issue during the next status meeting at the end of the week
B.
Escalate the issue to the project sponsor and upper management
C.
Close out the project and tell the manager to open a service desk ticket
D.
Log the issue and assign it to the project team member(s)
Your answer:
0 comments
Sorted by
Leave a comment first