Question 789 - PMP discussion

Report
Export

A project to develop a banking product is in the execution stage New regulations from the government are significantly affecting product development. Stakeholders are concerned about whether the planned benefits are still valid and achievable.

What should the project manager do first?

A.
Reforecast and revalidate the benefits baselines and targets
Answers
A.
Reforecast and revalidate the benefits baselines and targets
B.
Escalate the issue to the sponsor and request more funding.
Answers
B.
Escalate the issue to the sponsor and request more funding.
C.
Showcase progress toward the targets and revalidate a project work plan.
Answers
C.
Showcase progress toward the targets and revalidate a project work plan.
D.
Optimize alignment between the stakeholder needs and project objectives.
Answers
D.
Optimize alignment between the stakeholder needs and project objectives.
Suggested answer: C