ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 790 - PMP discussion

Report
Export

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

A.
Assign this member to facilitate the next meeting to ensure project team collaboration.
Answers
A.
Assign this member to facilitate the next meeting to ensure project team collaboration.
B.
Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.
Answers
B.
Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.
C.
Review and update the project ground rules to make meeting attendance mandatory.
Answers
C.
Review and update the project ground rules to make meeting attendance mandatory.
D.
Understand the reason for the team member's absence and encourage them to attend future meetings.
Answers
D.
Understand the reason for the team member's absence and encourage them to attend future meetings.
Suggested answer: B
asked 23/09/2024
Arun Samuel
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first