Question 791 - PMP discussion
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?
A.
Share unsuccessful results from previous projects with a similar scope
B.
Provide the failed test results along with the agreed-upon acceptance criteria
C.
Show that the acceptance criteria were changed by the vendor without approval.
D.
Document in the risk log that the issues in the system were already identified