A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?
A.
Assess the time overrun, and start implementation to avoid additional delays
B.
Motivate the team to avoid the frustration of working on a prolonged project
C.
Request a provisional budget increase to avoid any budget overruns
D.
Review the benefits of the proposed changes in relation to the business case