During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation.

How should the project manager respond?

A.
Offer guidance and follow up with some developmental activity for the junior team member.
Answers
A.
Offer guidance and follow up with some developmental activity for the junior team member.
B.
Refer the junior team member to the senior team member who develops the risk mitigation strategy.
Answers
B.
Refer the junior team member to the senior team member who develops the risk mitigation strategy.
C.
Inform the junior team member that risk mitigation is not part of their work.
Answers
C.
Inform the junior team member that risk mitigation is not part of their work.
D.
Tell the junior team member that the information is available in lessons learned.
Answers
D.
Tell the junior team member that the information is available in lessons learned.
Suggested answer: A

Explanation:

A single team member wouldn't develop risk strategies, that will likely either be up to an entire team or at minimum, the PM.