Question 817 - PMP discussion
A company is implementing a new system. The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies. The product owner is confused as to how to start delivering the functionalities required.
How should the project manager assist the product owner?
A.
Coach the product owner on how to create a product backlog.
B.
Discuss the product owner's responsibilities within the project team.
C.
Encourage the team to subdivide the project tasks.
D.
Create a work breakdown structure (WBS) and explain the deliverables to the product owner.