Question 889 - PMP discussion
To prevent influential stakeholders from dominating product delivery decisions, the product owner decided to use planning poker. What is a key advantage of using this technique?
A.
Assists the team in planning the activities within the iteration
B.
Allows for more accurate estimates
C.
Incorporates a technique similar to brainstorming
D.
Ensures active project team participation