A project is in the later stages of execution. The project engineer insists in every meeting that they were never consulted or informed of the project deliverables. However, the project manager communicated adequately and has the project engineer's approvals on record.

What should the project manager do?

A.
Write a formal letter to human resources (HR) detailing the project engineer's unprofessional behavior.
Answers
A.
Write a formal letter to human resources (HR) detailing the project engineer's unprofessional behavior.
B.
Approach the project engineer's supervisor about possibly replacing the project engineer.
Answers
B.
Approach the project engineer's supervisor about possibly replacing the project engineer.
C.
Introduce the item in the next meeting, reminding all stakeholders of the project objectives.
Answers
C.
Introduce the item in the next meeting, reminding all stakeholders of the project objectives.
D.
Engage the project engineer in a discussion to understand the concern and agree on a way forward.
Answers
D.
Engage the project engineer in a discussion to understand the concern and agree on a way forward.
Suggested answer: D