Question 891 - PMP discussion
As a project is ending, a business stakeholder requests information from the project manager regarding overall project performance to determine the success of the initiative. What should the project manager do to provide relevant information to the stakeholder?
A.
Update the project status report to include current performance information.
B.
Document the key performance indicators (KPIs) in the final project report.
C.
Document the project performance and influencing factors in the lessons learned register.
D.
Inform the stakeholder that performance will be evaluated three months after project closure.
Your answer: