A project manager is assigned to a parachute development project. Two of the key project resources have a disagreement regarding a requirement.
What should the project manager do?
A.
Refer to the ground rules that were set at the beginning of the project to help resolve the conflict.
B.
Reassign both of the resources to a different project to avoid conflict.
C.
Consider recommendations from a resource who has more experience with this situation.
D.
Define an action plan based on the project manager's experience.
Your answer: