During the execution phase, the project manager discovered that the deliverables are not meeting the quality specifications requested by the main stakeholder. This has caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost performance index (CPI) from 1.5 to 1.1.
What action should the project manager take to mitigate the issue of the deliverables being rejected during the next iteration?
A.
Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.
B.
Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.
C.
Create a dedicated sprint to complete all of the pending specifications from previous sprints.
D.
Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.