Question 914 - PMP discussion

Report
Export

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete.

The project manager reviews the work breakdown structure (WBS) and confirms that the component is included.

What does the project manager need to do first?

A.
Ask the project team to conduct a quality audit of the printing module components.
Answers
A.
Ask the project team to conduct a quality audit of the printing module components.
B.
Meet with the project team to understand the issue and define actions.
Answers
B.
Meet with the project team to understand the issue and define actions.
C.
Escalate this issue to the project sponsor immediately.
Answers
C.
Escalate this issue to the project sponsor immediately.
D.
Raise a change request to immediately implement the printing module component.
Answers
D.
Raise a change request to immediately implement the printing module component.
Suggested answer: B