Having managed a similar project while working with previous stakeholders, a project team decided to use the same report format they used in the earlier project. However, stakeholders new to the project are not fully comprehending the status of the project based on the reports that are being circulated.

How should the project manager address this concern moving forward?

A.
Add the issue to the issue log and determine the corrective action.
Answers
A.
Add the issue to the issue log and determine the corrective action.
B.
Create a fishbone diagram to determine the root cause for the misunderstanding.
Answers
B.
Create a fishbone diagram to determine the root cause for the misunderstanding.
C.
Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.
Answers
C.
Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.
D.
Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.
Answers
D.
Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.
Suggested answer: C