Question 923 - PMP discussion

Report
Export

A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project.

What should the project manager do to alleviate the stakeholders' concerns?

A.
Schedule a kick-off session to explain the problems of the project and gain approval and support.
Answers
A.
Schedule a kick-off session to explain the problems of the project and gain approval and support.
B.
Demonstrate the performance indexes and recommend corrective actions to the stakeholders.
Answers
B.
Demonstrate the performance indexes and recommend corrective actions to the stakeholders.
C.
Send communications for clarification so there is a full understanding about the situation.
Answers
C.
Send communications for clarification so there is a full understanding about the situation.
D.
Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders.
Answers
D.
Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders.
Suggested answer: B