Question 940 - PMP discussion
The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.
Which three techniques should the project manager use? (Choose three.)
A.
Gantt chart that includes milestones and deadlines
B.
Rolling wave planning and an adaptive approach
C.
Relative estimation to determine the task or deliverable sizes
D.
Iterations and reviews to continuously keep adapting the plan
E.
Bottom-up estimating based on a work breakdown structure (WBS)