During project execution, the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are only a few sprints remaining.

What should the project manager do?

A.
Provide testing training to all the project team members.
Answers
A.
Provide testing training to all the project team members.
B.
Add a new resource with testing skills to the team.
Answers
B.
Add a new resource with testing skills to the team.
C.
Work with the team to understand and solve the issues.
Answers
C.
Work with the team to understand and solve the issues.
D.
Increase the sprint duration so the testing can be completed.
Answers
D.
Increase the sprint duration so the testing can be completed.
Suggested answer: C