A project manager is leading a project when a major crisis suddenly causes an economic downturn, which may threaten the project outcome. What should the project manager do?

A.
Update the project charter and benefits management plan with the current realities.
Answers
A.
Update the project charter and benefits management plan with the current realities.
B.
Create a proposal suggesting that the project sponsor terminate the project.
Answers
B.
Create a proposal suggesting that the project sponsor terminate the project.
C.
Reallocate some project resources to other assignments in the organization.
Answers
C.
Reallocate some project resources to other assignments in the organization.
D.
Document the new risks in the project benefits management plan and risk management plan.
Answers
D.
Document the new risks in the project benefits management plan and risk management plan.
Suggested answer: D