Question 954 - PMP discussion
A company is set to execute a project across different localities and countries. Right before execution, a press release from one of the impacted communities expresses disapproval of the project.
What should the project manager do first?
A.
Engage all critical stakeholders and align project objectives with expectations from the community.
B.
Include the community statement as a new risk in the project's risk register.
C.
Approach the government to obtain their support and influence to engage the community.
D.
Update the stakeholder communications plan to ensure that the community is always informed.