Question 955 - PMP discussion
All activities for Project A are ahead of schedule, except for one activity that is on the critical path.
The resource manager is requesting that the team members join Project B, which is an important project in the organization that is behind schedule.
What should the project manager do?
A.
Ask the stakeholders to pause Project A because Project B is more important.
B.
Release the team members from Project A who are not working on a critical path activity,
C.
Agree to reassign all team members to Project B due to its importance.
D.
Retain the team members on Project A and complete the planned activities as committed.