Question 969 - PMP discussion
A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.
What should the project manager do next?
A.
Participate in the other project's daily standup meetings.
B.
Ask the other project manager to change the delivery methodology.
C.
Align with the other project manager's high-level project time lines.
D.
Request that the other project manager develop a work breakdown structure (WBS).