A team has noticed a labeling mistake in two different prototypes. The mistake resulted in a need to apply a different destructive testing plan for each prototype. This resulted in a decline in team morale.

What should the project lead do?

A.
Lead the team through the next sprint to prevent a similar issue.
Answers
A.
Lead the team through the next sprint to prevent a similar issue.
B.
Influence stakeholders to support the team allowing recovery within limits.
Answers
B.
Influence stakeholders to support the team allowing recovery within limits.
C.
Bring in subject matter experts (SMEs) to coach the team.
Answers
C.
Bring in subject matter experts (SMEs) to coach the team.
D.
Use cost and time contingencies to mitigate a project baseline impact.
Answers
D.
Use cost and time contingencies to mitigate a project baseline impact.
Suggested answer: B