An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager asks for a complete redesign of the functionality presented. The manager is new to the organization and has no experience with agile delivery.
What should the project lead do first?
A.
Ask the development team to explain how the functionality was implemented.
B.
Ask the manager for more details about their expectations for the functionality.
C.
Inform the manager that the agreed upon scope cannot be changed.
D.
Inform the manager that their request will be escalated to the project sponsor.
Your answer: