Question 966 - PMP discussion
A project manager is working on a project implementing a new time management system that will be rolled out in the next three months throughout the whole organization. Some managers have doubts about the transition period.
How should the project manager align with the managers during the rollout and cut over?
A.
Organize a sprint review for the new business units one month before the transition ends.
B.
Organize sprint reviews with the managers, grouping them based on hierarchy.
C.
Organize sprint reviews for all managers, grouping them based on the deployment schedule.
D.
Organize a full-day sprint review with all the senior managers in the organization.
Your answer: