ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 97

List of questions

Question 961

Report
Export
Collapse

A company is looking to adopt a new software solution to align business processes across multiple business units using a technology that was never used in the organization. What should the project manager focus on?

New system and the likelihood of technical debt
New system and the likelihood of technical debt
Specific requirements for important departments
Specific requirements for important departments
Out-of-scope requirements across the organization
Out-of-scope requirements across the organization
Conflicting priorities and business requirements
Conflicting priorities and business requirements
Suggested answer: D
asked 23/09/2024
Fatmata Kabba
51 questions

Question 962

Report
Export
Collapse

A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?

Net present value (NPV)
Net present value (NPV)
Earned value (EV)
Earned value (EV)
Impact value
Impact value
Expected monetary value (EMV)
Expected monetary value (EMV)
Suggested answer: A
asked 23/09/2024
Olaf Messerschmidt
31 questions

Question 963

Report
Export
Collapse

An organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief.

What should the project lead do?

Ask the solutions architect to contact the legal department and create the epic(s) in the product backlog.
Ask the solutions architect to contact the legal department and create the epic(s) in the product backlog.
Advise the SME that there are no legal requirements identified in the project brief and continue the workshop.
Advise the SME that there are no legal requirements identified in the project brief and continue the workshop.
Ask the project sponsor to contact the legal department and identify the legal impact.
Ask the project sponsor to contact the legal department and identify the legal impact.
Add the legal department to the list of stakeholders and contact them to discuss the project scope.
Add the legal department to the list of stakeholders and contact them to discuss the project scope.
Suggested answer: D
asked 23/09/2024
Lucie Loisel
39 questions

Question 964

Report
Export
Collapse

A member of an agile team constantly borrows the password to enter the software development platform. This situation has created a problem, because a version of the code was modified without authorization and nobody wants to take responsibility for this modification.

What should the project lead have done to prevent this situation?

Checked user permissions
Checked user permissions
Defined the ground rules
Defined the ground rules
Reviewed the security policies
Reviewed the security policies
Shared the code of ethics
Shared the code of ethics
Suggested answer: B
asked 23/09/2024
ali ghoubali
35 questions

Question 965

Report
Export
Collapse

A project manager is assigned to an analysis project for a customer. The project manager needs to keep the performance of the team a step ahead of the estimated delivery schedules.

What should the project manager do to impact the sprint cycles going forward on the project?

Build the capacity of the team to improve sprint cycles and provide weekly trend reports.
Build the capacity of the team to improve sprint cycles and provide weekly trend reports.
Engage an expert in project management to explain to the team how fast to work on the sprint cycle.
Engage an expert in project management to explain to the team how fast to work on the sprint cycle.
Work with the team on how to focus on only precommunicated project results.
Work with the team on how to focus on only precommunicated project results.
Train the team to analyze data and complete the user stories within the schedule.
Train the team to analyze data and complete the user stories within the schedule.
Suggested answer: A
asked 23/09/2024
John Ordonez
30 questions

Question 966

Report
Export
Collapse

A project manager is working on a project implementing a new time management system that will be rolled out in the next three months throughout the whole organization. Some managers have doubts about the transition period.

How should the project manager align with the managers during the rollout and cut over?

Organize a sprint review for the new business units one month before the transition ends.
Organize a sprint review for the new business units one month before the transition ends.
Organize sprint reviews with the managers, grouping them based on hierarchy.
Organize sprint reviews with the managers, grouping them based on hierarchy.
Organize sprint reviews for all managers, grouping them based on the deployment schedule.
Organize sprint reviews for all managers, grouping them based on the deployment schedule.
Organize a full-day sprint review with all the senior managers in the organization.
Organize a full-day sprint review with all the senior managers in the organization.
Suggested answer: C
asked 23/09/2024
Aldays Kausiona
43 questions

Question 967

Report
Export
Collapse

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager asks for a complete redesign of the functionality presented. The manager is new to the organization and has no experience with agile delivery.

What should the project lead do first?

Ask the development team to explain how the functionality was implemented.
Ask the development team to explain how the functionality was implemented.
Ask the manager for more details about their expectations for the functionality.
Ask the manager for more details about their expectations for the functionality.
Inform the manager that the agreed upon scope cannot be changed.
Inform the manager that the agreed upon scope cannot be changed.
Inform the manager that their request will be escalated to the project sponsor.
Inform the manager that their request will be escalated to the project sponsor.
Suggested answer: B
asked 23/09/2024
Sebasteen Lawrance
43 questions

Question 968

Report
Export
Collapse

A team has noticed a labeling mistake in two different prototypes. The mistake resulted in a need to apply a different destructive testing plan for each prototype. This resulted in a decline in team morale.

What should the project lead do?

Lead the team through the next sprint to prevent a similar issue.
Lead the team through the next sprint to prevent a similar issue.
Influence stakeholders to support the team allowing recovery within limits.
Influence stakeholders to support the team allowing recovery within limits.
Bring in subject matter experts (SMEs) to coach the team.
Bring in subject matter experts (SMEs) to coach the team.
Use cost and time contingencies to mitigate a project baseline impact.
Use cost and time contingencies to mitigate a project baseline impact.
Suggested answer: B
asked 23/09/2024
Darren Bajada
46 questions

Question 969

Report
Export
Collapse

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Participate in the other project's daily standup meetings.
Participate in the other project's daily standup meetings.
Ask the other project manager to change the delivery methodology.
Ask the other project manager to change the delivery methodology.
Align with the other project manager's high-level project time lines.
Align with the other project manager's high-level project time lines.
Request that the other project manager develop a work breakdown structure (WBS).
Request that the other project manager develop a work breakdown structure (WBS).
Suggested answer: C
asked 23/09/2024
Mahmoud Ismail
34 questions

Question 970

Report
Export
Collapse

A project manager is working on a software development contract. The project is halfway through a 3-year contract when there is a change in the political landscape and 20% of the stakeholders are replaced. Almost immediately decisions become delayed, invoices go unpaid, and meetings become unmanageable.

What tool would assist the project manager to better understand the new project landscape?

Communication analysis
Communication analysis
Power distance analysis
Power distance analysis
Stakeholder analysis
Stakeholder analysis
Engagement analysis
Engagement analysis
Suggested answer: C