ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 98

Add to Whishlist

List of questions

Question 971

Report Export Collapse

A project manager is managing a new type of project for a traditional organization. The culture of the organization is not typically in support of change.

Which two factors should the project manager consider in developing the portion of the project plan related to culture? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 972

Report Export Collapse

While preparing an earned value analysis (EVA) for a project sponsor, the project manager provides the following information in the latest project report:

Approved work package cost estimates: US$9,500

Contingency reserves: US$500

Management reserves: 10% of contingency reserves

Percent complete of the project: 50%

Planned percent of the project: 40%

Actual cost (AC) of the project: US$4,500

According to the project status, the current budget at completion (BAC) is considered achievable.

What value represents the cost performance required for the remaining work to keep the project cost goal within the baseline?

Become a Premium Member for full access
  Unlock Premium Member

Question 973

Report Export Collapse

A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 974

Report Export Collapse

A project manager has been working on a critical project to transform an organization's operations. The project manager had successfully completed four sprints when the innovation director was replaced. The new director placed a hold on the project until a new strategy can be put in place.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 975

Report Export Collapse

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.

What should the project manager recommend?

Become a Premium Member for full access
  Unlock Premium Member

Question 976

Report Export Collapse

Five project team members are working on a software development project. As the time line for the project is very tight, the members are working overtime to keep the project on schedule.

Recently, two members submitted resignations.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 977

Report Export Collapse

During a project kickoff meeting, the client indicates that the benefits of the project will become the most important revenue stream for the company. The client needs to find opportunities to deliver value to their company as soon as possible.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 978

Report Export Collapse

A project manager forms a new virtual project team that will be leading the project subcontractors in various countries. The project manager notices that each of the team members comes from a different culture.

Which action should the project manager take to increase team cohesiveness?

Become a Premium Member for full access
  Unlock Premium Member

Question 979

Report Export Collapse

A project in the execution phase is part of a large transformation program. The project manager for this project reports to a program manager and also heads the steering committee for this project. A steering committee meeting will be held in the following 2 weeks, during which the approach to measure the schedule performance of the project thus far will be presented.

What should the project manager do in preparation for this meeting?

Become a Premium Member for full access
  Unlock Premium Member

Question 980

Report Export Collapse

A project manager is leading a multiyear project. Near the end of the first year, the project manager checks to see if the whole budget allocated for the year will be used. Some features utilizing this year's budget were added later in the year as change requests, but these features will not be ready by the end of the first year.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions