ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 96

Add to Whishlist

List of questions

Question 951

Report Export Collapse

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

Become a Premium Member for full access
  Unlock Premium Member

Question 952

Report Export Collapse

An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.

How can the project manager ensure that the appropriate acceptance criteria are applied to the features?

Become a Premium Member for full access
  Unlock Premium Member

Question 953

Report Export Collapse

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 954

Report Export Collapse

A company is set to execute a project across different localities and countries. Right before execution, a press release from one of the impacted communities expresses disapproval of the project.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 955

Report Export Collapse

All activities for Project A are ahead of schedule, except for one activity that is on the critical path.

The resource manager is requesting that the team members join Project B, which is an important project in the organization that is behind schedule.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 956

Report Export Collapse

A project manager is assigned to a strategic communication project that involves subject matter experts (SMEs), interns, and new recruits. The project manager discovers that the project is not gaining much traction due to knowledge gaps from the interns. The budget for training is exhausted and the project needs to be delivered without delay.

Which two actions should the project manager take? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 957

Report Export Collapse

A project manager has been newly assigned to an existing project. The project manager noted that the input from a business unit, which is critical to the success of the project, was not included in any project assets. Instead, there were many complaints about the project's operational results and the alignment with solutions affected by the business unit's operations.

What action should the project manager take?

Become a Premium Member for full access
  Unlock Premium Member

Question 958

Report Export Collapse

During the fourth sprint, a project manager noticed that none of the customer representatives have participated in any of the sprints. The team told the project manager that they had a prototype ready.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 959

Report Export Collapse

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 960

Report Export Collapse

A project is on its second iteration out of eight. After some daily meetings, the project manager notices that one team member is always directing the meeting. The team is not comfortable with the situation and, as a result, the activities are blocked.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions