PMI PMP Practice Test - Questions Answers, Page 94
List of questions
Question 931

A project manager is working with an agile team to enhance a product. Due to a tight deadline, the team is trying to crash the schedule by engaging multiple resources to work on the project simultaneously. However, the technical environment is configured to allow only one resource to work on a feature at a time.
The team plans to upgrade the technical environment but is unable to agree on a way forward.
What should the project manager do first?
Question 932

One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager.
What should the project manager do?
Question 933

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a real-time manner.
What should the project manager do?
Question 934

A new project team has formed, and the project manager notices that some of the team members do not feel comfortable being part of the project team. As a result, members of the team are working individually and not as a team.
What should the project manager do to resolve this?
Question 935

A senior management team member contacts an agile project lead and mentions that certain features the senior manager thought would be in the current release were not included. What should the agile project lead do?
Question 936

An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed.
The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.
What should the project manager do to mitigate this risk?
Question 937

A project manager is in a team meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do?
Question 938

A pharmacy needs to launch a medication delivery service. An interdisciplinary team was created in order to have the service ready in one-month when it usually takes five months to complete.
What should the project manager do?
Question 939

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses. The country's economy is struggling, and some stakeholders cannot agree on this transformation need.
What should the project manager do?
Question 940

The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.
Which three techniques should the project manager use? (Choose three.)
Question