ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 94

Add to Whishlist

List of questions

Question 931

Report Export Collapse

A project manager is working with an agile team to enhance a product. Due to a tight deadline, the team is trying to crash the schedule by engaging multiple resources to work on the project simultaneously. However, the technical environment is configured to allow only one resource to work on a feature at a time.

The team plans to upgrade the technical environment but is unable to agree on a way forward.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 932

Report Export Collapse

One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 933

Report Export Collapse

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a real-time manner.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 934

Report Export Collapse

A new project team has formed, and the project manager notices that some of the team members do not feel comfortable being part of the project team. As a result, members of the team are working individually and not as a team.

What should the project manager do to resolve this?

Become a Premium Member for full access
  Unlock Premium Member

Question 935

Report Export Collapse

A senior management team member contacts an agile project lead and mentions that certain features the senior manager thought would be in the current release were not included. What should the agile project lead do?

Become a Premium Member for full access
  Unlock Premium Member

Question 936

Report Export Collapse

An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed.

The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.

What should the project manager do to mitigate this risk?

Become a Premium Member for full access
  Unlock Premium Member

Question 937

Report Export Collapse

A project manager is in a team meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 938

Report Export Collapse

A pharmacy needs to launch a medication delivery service. An interdisciplinary team was created in order to have the service ready in one-month when it usually takes five months to complete.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 939

Report Export Collapse

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses. The country's economy is struggling, and some stakeholders cannot agree on this transformation need.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 940

Report Export Collapse

The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.

Which three techniques should the project manager use? (Choose three.)

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions